Fairhaven dependency register review, status window of Sep 28

Fairhaven dependency register review, status window of Sep 28

A program director reviewing cross-team dependencies

Dependency review Fairhaven Home Stores Ferncastle Operations Group

Owner: Philippa Sinclair. Updated Oct 1, 2026.

The open dependencies

Status window closed Sep 28, 2026 1 dependency without a Fairhaven owner Oldest open 34 days

Every cross-workstream dependency of the Fairhaven store operations improvement program that was still open on Monday, September 28, 2026, tied to a Fairhaven owner, a due date and the milestone it holds up, with the one that has no owner marked for escalation. Prepared by Philippa Sinclair, program director at Ferncastle Operations Group, for Gareth Pryce, chief operating officer at Fairhaven Home Stores, and the Fairhaven workstream owners. Since the program started in June, 23 dependencies have been logged: 17 are closed and 6 are open. Two of the open six had no owner on the Fairhaven side until Sep 24, when Gareth Pryce assigned the store system data extract to the IT director. One still has none.

Open dependencies6of 23 logged since June
Without a Fairhaven owner1Loss prevention data access
Oldest open34days, Store system data extract
Closed in the last fortnight4Sep 14 to Sep 28 windows

The register groups every open dependency by status, and each card shows the owner, the due date and the milestone it holds up. Six are open: one is Escalated (Store system data extract), one is Waiting for owner (Loss prevention data access) and four are Owned. Read the Waiting for owner and Escalated groups first, because nothing moves in them until a person acts.

Six dependencies, each with an owner and a milestone

Days open are counted to Sep 28. Owner is the Ferncastle person who chases it; Fairhaven owner is the person who has to deliver it.

DependencyStatusFairhaven ownerOwnerHolds upDueDays open
Store system data extractEscalatedIT directorEmeka AchebeReplenishment pilotOct 934
Shift template sign-off by HROwnedHR leadHamish AldousLabor scheduling pilotOct 521
Planogram file for the pilot storesOwnedMerchandising managerSaoirse QuigleyReplenishment pilotOct 616
Loss prevention data accessWaiting for ownerNonePhilippa SinclairShrink baselineNo date12
Distribution center slotting windowOwnedDC operations managerHamish AldousDC flow wave 2Oct 129
Store manager briefing slotOwnedRegional operations managerEmeka AchebeLabor scheduling pilotOct 74

What each one needs next. The data extract needs confirmation that Fairhaven IT has scheduled it. HR needs to give a sign-off date for the new shift template. The planogram file covered 9 of the 12 pilot stores when it was sent in August, so the file for the three missing stores is outstanding. The slotting window is a two-day window at the second distribution center outside the peak receiving days, and its dates are still to agree. The briefing slot is 30 minutes in the Oct 7 regional store manager call.

How old they are

Three of the six open dependencies are older than 15 days: Store system data extract (34 days), Shift template sign-off by HR (21) and Planogram file for the pilot stores (16). Two are 7 to 14 days old and one is under 7 days. Age is counted from the day the dependency was raised, not from its due date, so a dependency can be old and still on time.

What changed in the fortnight

Seven dependencies were open at the Sep 14 window. Three were raised since: Loss prevention data access on Sep 16, Distribution center slotting window on Sep 19 and Store manager briefing slot on Sep 24. Four were closed. Six are open now. A raised dependency and a closed dependency are counted separately, never netted off.

Escalation rules

Details
No Fairhaven owner by day 10The program director asks the sponsor to name an owner at the next steering meeting. The status stays Waiting for owner until someone accepts it.
Open 30 days or moreEscalated to the sponsor, who names or confirms the owner and a due date. The store system data extract reached 30 days on Sep 24 and was assigned to the IT director that day.
Past its due dateThe Fairhaven owner gives a new date within two working days, and the milestone it holds up is re-dated or marked at risk.
Holds up a milestone due within 14 daysChecked at the weekly review, not only at steering.
ClosingClosed only when the Fairhaven owner confirms the commitment was met and the milestone it held up is released.

Loss prevention data access has no Fairhaven owner

Philippa Sinclair raised this dependency on Sep 16. It is 12 days old on Sep 28 and it passed the 10 day mark on Sep 26. The shrink baseline cannot be agreed without read access to the loss prevention system, and nobody on the Fairhaven side has accepted the request, so it has no due date.What it holds up. The access request is drafted but cannot be sent without a Fairhaven owner. The shrink baseline method draft, due Oct 23, starts only once access is granted. Consequence. Without a baseline, shrink results cannot be shown as a change at the November value review. Ask. Gareth Pryce names an owner at the Oct 8 steering meeting.

Recovery steps

The recovery path for the dependency without an owner, from the day it was raised to the first usable baseline:

✓Raised Sep 16, Ferncastle owner set
✓Day 10 passed on Sep 26, no owner
Sponsor asked at steering, Oct 8
Fairhaven owner accepts and sets a due date
Access request sent, due Oct 9
Baseline method drafted, due Oct 23

The two aged dependencies and the planogram file each have their own recovery path:

Loss prevention data access

Waiting for owner Owner: Philippa Sinclair

Path. Gareth Pryce names a Fairhaven owner on Oct 8. The owner accepts, sets a due date and approves the access request that Philippa has drafted. Saoirse Quigley then starts the shrink baseline method.

If no owner is named on Oct 8. The baseline method cannot start, the baseline cannot be agreed with the loss prevention lead before the November value review, and shrink stays not measurable.

Store system data extract

Escalated Fairhaven owner: IT director

Path. The IT director confirms the extract is scheduled and gives the date of the first daily extract of store stock positions. Saoirse Quigley then re-runs the store stock test on a one-week sample (due Oct 12). Owner on the Ferncastle side: Emeka Achebe.

If it is not scheduled by Oct 9. The Oct 16 replenishment pilot date resets for a second time, and Gareth Pryce decides whether to hold it.

Planogram file

Owned Fairhaven owner: Merchandising manager

Path. The merchandising manager sends the current planogram for the three pilot stores missing from the August file, due Oct 6. Saoirse Quigley checks it against the replenishment rules for all 12 pilot stores.

If it is late. The replenishment rules cannot be confirmed for three stores, and the Oct 16 pilot start is at risk for them.

Before the Oct 8 steering meeting
✓Review the six open dependencies at the Sep 28 status window. Owner: Philippa Sinclair, done
Receive the planogram file for the three missing stores. Owner: Saoirse Quigley, Oct 6
Confirm the briefing slot in the Oct 7 regional call. Owner: Emeka Achebe, Oct 7
Ask the HR lead for the shift template sign-off date. Owner: Hamish Aldous, before Oct 8
Confirm the store system data extract is scheduled. Owner: Emeka Achebe with the IT director, Oct 9
Agree the slotting window dates with the DC operations manager. Owner: Hamish Aldous, Oct 12
Ask Gareth Pryce to name an owner for loss prevention data access. Owner: Philippa Sinclair, Oct 8

Who is on this review

PSPhilippa SinclairProgram director, Ferncastle Operations Group, owns the review
HAHamish AldousWorkstream lead, Ferncastle Operations Group, owns the HR and slotting dependencies
GPGareth PryceChief operating officer, Fairhaven Home Stores, names the missing owner

Demo client portal. Ferncastle Operations Group, Fairhaven Home Stores, the people and every figure are fictional sample data. Built on FuseBase.