Owner: Marguerite Toussaint. Updated Sep 28, 2026.
Every pending submittal and open RFI on the Ridgeview Medical Office Building mechanical package, with the business days it has waited against the 10 business day response window, whose court it sits in, and what has to happen to get the air handling unit submittal at revision 2 answered. Prepared weekly by the Ironvale project engineer for the Brackenhurst Builders project manager and the design team.
Since Aug 20, Ironvale Mechanical has logged 18 submittals and 11 RFIs, 29 items in all. Twenty-two are answered. Seven are pending: 4 submittals and 3 RFIs. Two of the pending submittals are past the window, and both sit with the design team.
The window is 10 business days. The bars count business days from the day the item was logged as submitted to Sep 28. Anything above 10 is past the window. The air handling unit submittal at revision 2 is highlighted at 13 business days, and the hydronic pumps submittal follows at 11.
Each square is one submittal. Fourteen are answered, 2 are pending inside the window and 2 are pending past it.
Waiting days are business days at Sep 28. The window ends 10 business days after the item was logged. RFIs are marked in the item name.
| Item | Drawing or spec | Waiting | Window ends | Court | State |
|---|---|---|---|---|---|
| Air handling unit, revision 2 | Spec 23 73 00, sheet M-501 | 13 | Sep 23 | Design team, mechanical engineer | |
| Hydronic pumps | Spec 23 21 23, sheet M-401 | 11 | Sep 25 | Design team, mechanical engineer | |
| Roof curb elevation, RFI | Sheets A-301 and M-101 | 7 | Oct 1 | Design team, architect | |
| Variable air volume boxes | Spec 23 36 00 | 6 | Oct 2 | Design team, mechanical engineer | |
| Plumbing fixtures | Spec 22 40 00 | 4 | Oct 6 | Brackenhurst, review before it goes to the design team | |
| Fire damper access, RFI | Sheet M-202 | 4 | Oct 6 | Ironvale, sketch requested by the design team | |
| Slab sleeve locations, RFI | Sheet S-201 | 2 | Oct 8 | Brackenhurst, structural engineer through the project manager |
Four items sit with the design team, two with Brackenhurst and one with Ironvale. The roof curb elevation RFI reaches the end of its window on Oct 1, so it is the next item to turn red if no answer comes back.
The ceiling grid RFI is counted among the 8 answered RFIs as of the date of the email, but that answer went by email to the foreman and was never recorded, so it is not a field instruction until Brackenhurst resends it through the record. The field followed a response the office had not seen. Dominic Ostrowski ruled that only the recorded response is the field instruction, and he asked Brackenhurst to resend the answer through the record.
An answer that is not in the record is not an instruction. The crew follows the recorded response and nothing else.
Air handling unit submittal, revision 2: 13 business days, 3 days past the window
Ironvale resubmitted the air handling unit at revision 2 on Sep 9. The window ended Sep 23, and no response has come back. The submittal sits with the design team's mechanical engineer.What it holds up. Release for fabrication and the delivery date for the unit. The hydronic pumps submittal, at 11 business days, is the second item past the window and holds up the pump release. Consequence. Until both are answered, Ironvale cannot confirm equipment delivery dates for the mechanical rooms. Ask. The Brackenhurst project manager asks the design team for a recorded response on both before the Oct 9 look-ahead meeting.
RFIs answered, 8 of 11
Demo deal room. Ironvale Mechanical, Brackenhurst Builders, the people and every figure are fictional sample data. Built on FuseBase.