Ridgeview change event decision sheet

Ridgeview change event decision sheet

Two project managers discussing a duct conflict in an unfinished ceiling space

Change sheet Brackenhurst Builders Ironvale Mechanical

Owner: Dominic Ostrowski. Updated Sep 28, 2026.

The nine change events

State on Sep 28, 2026 2 events waiting on Brackenhurst Work stopped on the duct conflict

Each change event logged on the Ridgeview Medical Office Building mechanical package, with its estimate, the hours already worked and the decision Brackenhurst Builders has to make, so the concealed duct conflict is authorized or declined before more hours are spent. Prepared by Dominic Ostrowski, Ironvale Mechanical project manager, for the Brackenhurst project manager and Anjali Venkataraman.

Nine change events have been logged since mobilization. Five are authorized, 2 are declined and 2 wait on a Brackenhurst decision. The working rule is plain: no extra work before written authorization.

Events logged9Since mobilization
Authorized38.6thousand USD5 events
Waiting for the customer2Duct conflict, thermostat wiring
Hours before authorization14hours, Concealed duct conflict

The table lists every event with its decision, its estimate and the hours crews worked before the decision. Eight events show 0 hours. One shows 14.

Five authorized, two declined

Authorized events are priced, approved inside Ironvale and approved in writing by Brackenhurst. Their work orders show where the work stands.

Change eventWork orderEstimateWork order statusCustomer approval
Rooftop unit curb adaptersWO-3101$12,400On siteApproved
Hydronic isolation valvesWO-3102$9,800CompleteApproved
Exhaust fan riser relocationWO-3103$7,100Ready to reviewApproved
Condensate pump additionWO-3104$5,600Scheduled for Oct 5Approved
Floor drain additionWO-3105$3,700CompleteApproved
Pipe insulation upgradeWO-3106$2,200No work performedDeclined
Access panels additionWO-3107$1,500No work performedDeclined

The five authorized events total $38,600. The two declined events were priced at $2,200 and $1,500, and no crew time went into either. The rooftop unit curb adapters are a separate matter from the rooftop unit curb supply question: the adapters are authorized, and the supply question sits in the scope review with Anjali Venkataraman.

From logged to authorized

Of 9 events logged, 2 were declined and 2 are still waiting, which leaves 5 authorized. The waiting two are the only events that can still change the authorized total.

Decision states

Details
Event loggedThe foreman or the project manager has recorded the condition with field photos and the contract scope it touches. No price yet.
PricingThe project manager builds the estimate from labor and material input. Crews do not start work on a priced event.
Internal approvalDominic Ostrowski approves the price and the schedule effect before it goes to Brackenhurst.
Customer decisionBrackenhurst accepts, declines or asks a question in writing. The answer is recorded on the work order.
Authorized or declinedAuthorized releases the field task. Declined closes it and the crew does not start.
Waiting for the customerPriced and sent to Brackenhurst, with no written answer yet. No crew hours go on it until the answer is recorded.

The concealed duct conflict

Concealed duct conflict: priced at $7,450, further work stopped

Crews found the conflict in the third floor ceiling space on Sep 22. Ironvale priced the change at $7,450. Before it was priced, crews logged 14 labor hours on it, because the foreman had been told to keep the floor moving. That broke the working rule of no extra work before written authorization.What Ironvale did. Dominic Ostrowski priced the change and stopped further work on it. The work order WO-3108 shows Needs follow-up and Urgent. What Brackenhurst decides. Anjali Venkataraman decides authorization at the Thursday meeting, and the decision is recorded by Oct 6. Whether the 14 hours are part of the authorized price is part of that decision, and Ironvale does not assume they will be. Consequence. Until the decision is recorded, the third floor ceiling space stays as it is and no more hours go on this event.

The second waiting event is the thermostat wiring relocation, WO-3109, estimated at $3,200. Its status is New and its owner is Marguerite Toussaint. No work starts on it until Brackenhurst decides.

How an event moves

✓Event logged
✓Priced
✓Internal approval
Customer decision
Authorized or declined
  • Event logged: Field photos and the contract scope it touches
  • Priced: Built from labor and material input
  • Internal approval: Dominic approves the price and the schedule effect
  • Customer decision: Authorize, decline or ask a question in writing
  • Authorized or declined: Authorized releases the field task, declined closes it

Authorization steps for the duct conflict

✓Found Sep 22, event logged
✓Priced at $7,450
✓Internal approval, work stopped
Customer decision, Thursday meeting
Decision recorded by Oct 6
Crew released or event closed
Before work on the duct conflict restarts
✓Price the change and stop further work. Owner: Dominic Ostrowski, done
Decide authorization at the Thursday meeting. Owner: Anjali Venkataraman, Thursday
Record the authorization or decline in writing on WO-3108. Owner: Anjali Venkataraman, Oct 6
Release the crew on authorization, or close the event on a decline. Owner: Marguerite Toussaint, within 1 business day of the record
Decide the thermostat wiring relocation, WO-3109. Owner: Anjali Venkataraman, next Brackenhurst meeting

Decision record

AVAnjali VenkataramanProject executive, Brackenhurst Builders, signs the customer decision
DODominic OstrowskiProject manager, Ironvale Mechanical, prices and approves the event
MTMarguerite ToussaintProject operations manager, Ironvale Mechanical, dispatches the crew after the decision
EventCustomer decisionSigned byDate
Concealed duct conflict, WO-3108PendingAnjali VenkataramanRecord by Oct 6
Thermostat wiring relocation, WO-3109PendingAnjali VenkataramanNot yet set