Verrano Summit client change decision log

An event producer and a client reviewing a change request on a venue floor during build

Change decision log Verrano Instruments Sablewood Events

Owner: Kofi Adjei. Updated Sep 28, 2026.

Changes at a glance

Status as of Sep 28, 2026 2 changes waiting on a decision 1 change started before a decision

Every change Verrano Instruments has requested for the Verrano Summit 2026 on November 12 and 13, with its price and its decision, so that no work starts before the decision is recorded. Prepared by the Sablewood producer for Nathaniel Obuya, Head of marketing events at Verrano Instruments, and for Verrano procurement. Fourteen changes are logged: 6 included at no cost, 4 priced and accepted for $21,300 in total, 2 declined and 2 waiting on a decision.

Changes logged14since kickoff
Waiting on a decision2both decided by Oct 8
Priced and accepted21.3thousand USD4 changes
Absorbed by Sablewood1.9thousand USDstage extension

Changes by area of the event

Read the table by row. Each row is an area of the summit and each column is a decision state, so the numbers across a row add up to the total for that area. Agenda and sessions has the most changes (4). Stage and set and Agenda and sessions each hold one change that is still waiting on a decision.

What is waiting on Verrano

Two changes have no decision yet. Both will be priced before any supplier call, and both are decided by Oct 8.

ChangeStatus in the logNeedsDate
Keynote stage layoutClient review UrgentKeynote format decision from Nathaniel Obuya; the staging quote expired on Sep 25 with a $3,200 reprice riskFormat by Oct 7, decision by Oct 8
Customer panel sessionClient review HighPrice set by Sablewood; the room depends on the breakout room changeDecision by Oct 8

From requested to accepted

The chart starts at the 14 changes requested. It takes off the 2 declined and the 2 waiting, which leaves 10 that are included or priced and accepted. Those 10 split into 6 included at no cost and 4 priced and accepted.

The four outcomes, with the exact changes in each:

Included at no cost (6)

ChangeAreaStatus
Stage extensionStage and setIn production
Day 1 afternoon sessionAgenda and sessionsPlanning
Breakout moderator swapAgenda and sessionsComplete
Late registration deskRegistration and badgingPlanning
Gluten free stationCatering and hospitalityConfirmed
Keynote speaker hotel nightSpeaker travelPlanning

The stage extension is on this list because Sablewood absorbed its cost, as the callout below explains.

Priced and accepted (4)

ChangeSupplierPriceStatus
Keynote stage lightingPennywhistle Audio Visual$8,200Confirmed
Day 2 closing extensionPennywhistle Audio Visual$5,400Confirmed
Plated lunch upgradeFairweather Catering$4,700Confirmed
Speaker highlight reelQuillhaven Film Studio$3,000In production

The four prices add up to $21,300.

Declined (2)

ChangeSupplierWhat happened
Late night receptionFairweather CateringDeclined; no supplier work booked
Same day video editQuillhaven Film StudioDeclined; no supplier work booked

Both rows show Complete in the log because the decision is closed.

Waiting on a decision (2)

Keynote stage layout and Customer panel session. Both are in Client review and both need a decision from Nathaniel Obuya by Oct 8.

No work before a decision

The change rule

Details
Change ruleNo production work before a recorded inclusion or price decision.
Where requests goThrough the project space only. Nathaniel Obuya agreed to send every request there, so a text message or a hallway request is not yet a request.
Who checks feasibilitySimone Vrabec, Executive producer, with the supplier named in the log.
Who decides the commercial outcomeKofi Adjei, Managing director: included, priced, absorbed or declined. Both open changes are priced before any supplier call.
Who approvesNathaniel Obuya approves the change inclusion and price. The approved version returns to the log and only then does supplier work start.
What the log countsEach change shows requested, priced, decided and accepted, plus any cost absorbed and any work started before a decision.

Stage extension: started before any decision, $1,900 absorbed

The request to extend the main stage reached a Sablewood producer by text message during a site visit. Work started on Aug 18 with Brindlemoor Staging and the request never reached the change record until Brindlemoor invoiced it. Sablewood absorbed the $1,900, so Verrano pays nothing for it, and the change is included at no cost.Why it matters. This is the one change in the log that started before a decision. It is the reason the rule above exists and the reason the log counts work started before decision. The extension is still In production and due Oct 8.

Approval steps for a client change

✓Request logged in the project space
✓Feasibility checked by the producer
✓Inclusion and price set by Kofi Adjei for 12 changes
Price the two open changes, Oct 5
Verrano decision on the two open changes, Oct 8
Supplier work booked
Accepted version recorded in the log
Before Oct 8
✓Agree that requests go through the project space only. Owner: Nathaniel Obuya, done
Price the Keynote stage layout and the Customer panel session before any supplier call. Owner: Kofi Adjei, Oct 5
Choose the keynote format so Brindlemoor Staging can reprice. Owner: Nathaniel Obuya, Oct 7
Decide both open changes. Owner: Nathaniel Obuya, Oct 8
Record both decisions in the log and book supplier work. Owner: Simone Vrabec, Oct 9

A change is real when it has a price and a decision in the log. Until then it is a question, and no supplier gets a call.

Kofi AdjeiManaging director, Sablewood Events

Who is on this log

NONathaniel ObuyaHead of marketing events, Verrano Instruments, approves each change
KAKofi AdjeiManaging director, Sablewood Events, decides included, priced, absorbed or declined
SVSimone VrabecExecutive producer, Sablewood Events, checks feasibility and books supplier work